Construction Updates

Completed Projects

Project NameStartOpenPercent Complete
10 Classroom AdditionSpring 2022Winter 2022100%

Projects In Progress

Project NameStartOpenPercent Complete
Perimeter FencingReceiving QuotesSummer 20230%

Completed Projects

Project NameStartOpenPercent Complete
12 Classroom AdditionFall 2020Summer 2021100%

Projects In Progress

Project NameStartOpenPercent Complete
Roof Replacement4/20/2023Summer 202390%
Perimeter FencingReceiving QuotesSummer 20230%

Completed Projects

Main Building

 

Project NameStartOpenPercent Complete
Front Hall/Foyer DoorsSpring 2022Winter 2022100%
Parking Lot PavingSpring 2022Fall 2022100%
Security and Access ControlSummer 2022Fall 2022100%
Additional Modular ClassroomsSpring 2021/22Summer 2021/22100%
New Intercom SystemFall 2022Winter 2022

100%

Restroom Remodel2/10/20237/23/2023100%
Athletic Complex

Project NameStartOpenPercent Complete
Baseball Press Box and BleachersSpring 2021Summer 2021100%
Softball Press Box and BleachersSpring 2021Summer 2021100%
Dugouts - Baseball and SoftballSpring 2022Fall 2022100%
Batting CagesSpring 2022Fall 2022100%
Plaza Area UpgradesSummer 2023Fall 2023100%

 

Projects In Progress

Main Building

 

Project NameStartOpenPercent Complete
Roof ReplacementPre-Con 4/19/2023TBD40%
Gym Locker Rooms RemodelPre-Con 3/23/23Summer 202325%

 

Athletic Complex

COMPLETED PROJECTS

.
Project NameStartOpenPercent Complete
CARE Program RemodelFall 2022Spring 2023100%
Replace Front EntranceSpring 2023Spring 2023100%
Security UpgradesSpring 2023Spring 2023100%

Completed Projects

Project NameStartOpenPercent Complete
Main Office ConstructionSpring 2022Summer 2022100%

Projects in Progress